Autumn 2023 – Construction Update

March 21, 2023

Stages 65 & 67

Construction of the 48 lots in Stages 65 & 67 is nearing completion, with Practical Completion (PC) of the civil works scheduled for 21/03/2023.

Titles are anticipated in May.

Image of Stage 65, Ashdown Drive looking north.

Image of Stage 65, Ashdown Drive looking north.

 

:  Image of Cnr. Ashdown Drive & Salisbury Avenue in Stage 67

Image of Cnr. Ashdown Drive & Salisbury Avenue in Stage 67.

 

Image of Stage 65, Ashdown Drive looking south.

Image of Stage 65, Ashdown Drive looking south.

 

Footpath construction on Salisbury Avenue (Stage 67).

Image of footpath construction on Salisbury Avenue (Stage 67).

 

Stages 68 & 69

Preliminary earthworks have been completed. Civil works are expected to commence shortly, once the Council signs off on the Engineering plans. Titles are expected in September.

Image of Stage 67 and future Stages north.

Image of Stage 67 and future stages north.

 

Stages 70, 71 & 72

Preliminary earthworks are continuing. Civil works are expected to start around May/June and Titles in February 2024.