Stage 48 & 49  (30 Lots)

These Lots titled in May and the last few are presently being fenced.

IMG_5827

Stage 50 & 51  (38 Lots)

Our newly minted Lots in Stages 50 & 51 have achieved Practical Completion and are going through the compliance stage. 

Titles are on track for issue late June and settlements early July.

IMG_5817

 

IMG_5822

IMG_5823

 

IMG_5829

Stage 52 & 53 (29 Lots)

Construction is well underway with water, sewer, power and communications all installed, most of the bulk earthworks and some of the footpaths.  Titles and settlements are on track for September.